A robust plan for discharging the liabilities associated with a facility’s operation is important not just for compliance with legislation but to establish the correct basis for funding and implementing safe, environmentally sound, and cost effective decommissioning for that facility whether it be nuclear, conventionally hazardous, or physically complex. The plan will form the basis on which work is presented to market and, once contracted, performance monitored.

The UK’s Nuclear Decommissioning Authority terminated a major clean up contract for 12 nuclear sites earlier in 2017 because of the emergent mismatch between the work that was specified in that contract which dated to 2012, and an emerging work that actually needed to be done (click here to see Prospect blog covering Written Statement to Parliament by Energy Secretary Greg Clark on 27 March 2017) While this was no reflection on the performance of the contractor it did illustrate the desirability of having a fully underpinned decommissioning baseline plan prior to any commercial commitment.

Of course the robustness of the baseline will be a function of the time prior to executing the work: while it is self evident that however well you plan, time and the reality on the ground will act to confound that plan, this should not put off the need for proper underpinning at appropriate points through the lifecycle of the facility irrespective of whether that facility is nuclear or conventional.

In that regard treatment of risk and uncertainty is a key factor. While this is recognised, rigorous analysis can often be overlooked when it comes to developing a decommissioning plan.

There are two principle objectives to risk and uncertainty analysis – informing contingency values in the cost estimate and identifying work required to mitigate or to retire each risk.  While the former is well recognised the influence of the latter may not be, especially if budgets are tight. To help address this the UK has implemented a formalised and structured approach to risk mitigation within decommissioning planning, with its own technical baseline specifying for each relevant risk the work needed, timescale, owner and cost. Crucially this approach links execution of the work to the timescale required for the ‘solution’ within the decommissioning plan (which in turn influences, and should reduce, the cost contingency value going forward).  Parking or transferring risk should not normally be an option: the operator should implement measures to address these even if not under its direct control.

For this reason and others there are obvious attractions to both the operator and the regulator in having the facility’s decommissioning plan independently verified in order to provide assurance to regulators, funding bodies, and others that the liabilities attaching to that facility can be discharged safely, cost effectively and in an environmentally responsible manner.

Please click here for an appendix covering factors any decommissioning plan should take into account

Prospect Law and Prospect Advisory provide a unique combination of legal and technical advisory services for clients involved in energy, infrastructure and natural resource projects in the UK and internationally.       

Chris Kaye is a nuclear specialist and senior commercial executive with over 40 years experience in negotiating, managing, and assuring the performance of multi-billion pound strategically and technically complex contracts, to Board and Ministerial level, within Government and private sectors. From 2006 and prior to joining Prospect Group in 2017 Chris was a function head of a major UK Non-Departmental Public Body. There he was responsible for assurance and oversight of all the UK private sector nuclear operators’ decommissioning strategies, plans and costings on behalf of the UK Government where a third party or the taxpayer has an interest in funding and risk.

This article remains the copyright property of Prospect Law Ltd and Prospect Advisory Ltd and neither the article nor any part of it may be published or copied without the prior written permission of the directors of Prospect Law and Prospect Advisory.

For more information please contact us on 020 7947 5354 or by email on:

For a PDF of this blog click here

Share on FacebookShare on Google+Tweet about this on TwitterShare on LinkedInShare on StumbleUponBuffer this pageEmail this to someone